Daye hydrogen base reaches 90% construction progress as storage tanks enter testing stage
Three hydrogen storage spheres have completed main installation and welding; heat treatment and pressure and leak tests remain before operation.

The story explained
A field report published by the Daye government on 15 November states that construction of the Lingkong hydrogen industrial base in Nanshi village, Huandiqiao, was about 90% complete as of 12 November. Work has moved into equipment installation and performance testing. Hubei Lvye Hydrogen Energy, part of Hubei Guanggu East Holding Group, owns the project, which began construction in March.
Main assembly and welding are complete on three spherical hydrogen storage vessels. The report quotes the project chief engineer describing 14-metre-high vessels, a design operating pressure of 1.6 MPa and a rated storage volume of 3,000 cubic metres. It does not clarify the reference conditions for that volume or whether it applies to one vessel or the group, so no hydrogen mass conversion is made here. Heat treatment is beginning, with hydrostatic and leak testing and acceptance still to follow.
Two screw refrigeration units have been secured to their foundations, the main hydrogen pipeline has been laid, and chilled-water tanks, air compressors and nitrogen-generation equipment are in position. Water treatment and compression and purification systems remain under installation; equipment placement does not establish completion of integrated commissioning.
The base uses alkaline water electrolysis with a supply arrangement combining grid power, distributed solar and energy storage. The report describes a planned output of more than 3,000 tonnes of green hydrogen a year at full capacity, primarily for local buses, mining trucks and logistics vehicles. These are capacity and application plans, not measured production or delivered hydrogen volumes.
Why it matters
Editorial assessment: The next integration issues concern vessel testing, hydrogen piping and cooling-system interfaces. The report identifies no valve orders.
Relevant toProject owners, EPC contractors and valve, pump and process-control specialists
What to watch next
Follow pressure and leak testing, integrated commissioning and operating acceptance, and clarification of the storage-volume basis.
These are research prompts, not announced tenders or confirmed subsequent developments.
大冶市人民政府网站/云上大冶
3000方核心储氢设施完工 临空氢能基地建设提速
This is an independently written summary and analysis, not an official translation. Project plans and status may change.