Wuhan's Dongxihu district reported on 17 November that phase three of Hanxi wastewater treatment plant was completed and operating. The addition provides 200,000 tonnes/day, taking total capacity from 600,000 to 800,000 tonnes/day. The exact start-up date was not specified.

The story explained
Wuhan’s Dongxihu district reported on 17 November that phase three of Hanxi wastewater treatment plant was completed and operating. The addition provides 200,000 tonnes/day, taking total capacity from 600,000 to 800,000 tonnes/day. The exact start-up date was not specified.
Biological and secondary-settlement tanks are stacked with an intermediate equipment operating level to fit the constrained site. The district reports plant effluent at Class 1A and several key phase-three indicators at surface-water Class IV; that is not a claim that every indicator meets Class IV.
Treated water supports local waterways, washing and landscaping. Two hydropower units on dedicated piping use the elevation difference and are connected for on-site consumption. The capacity announcement concerns operating infrastructure, without a new pump or valve procurement schedule.
Why it matters
Editorial assessment: Stacked treatment warrants attention to maintenance access, level control and piping isolation; operation does not establish new orders.
Relevant toProject owners, EPCs and valve, pump and process-control professionals
What to watch next
Monitor effluent quality, maintenance and water reuse.
These are research prompts, not announced tenders or confirmed subsequent developments.
武汉市东西湖区水务和湖泊局/区融媒体中心
作用大!颜值高!全省首座“立体式”污水处理厂就在东西湖
This is an independently written summary and analysis, not an official translation. Project plans and status may change.