ChemicalsProject watch

Lianjiang electrolyte project names provisional valve supplier at RMB 2.85 million

Curated by valve.market · China
Persistent browser storage is unavailable.
IN BRIEF

Xintai Valve Group ranks first in the November 3 notice for the project's second valve-material procurement. The objection period runs through November 5.

Added: 2026.11.04Source language: Chinese
Illustrative industrial facility; not the Lianjiang electrolyte project.
Illustrative industrial facility; not the Lianjiang electrolyte project. Image: Wolfgang Weiser / Unsplash
Organizations湖北省工业建筑集团安装工程有限公司;胜华连江
Location / scopeLianjiang, Fujian
Announced stageProvisional award notice
01

The story explained

A November 3 notice names Xintai Valve Group as the provisional supplier for the second valve-material procurement for Shenghua Lianjiang’s 200,000-tonne lithium-battery electrolyte installation project. Its submitted package price is RMB 2.85 million.

The procurement was advertised on October 20 and bids were opened and evaluated online on October 26. The purchaser is the installation-engineering subsidiary of Hubei Industrial Construction Group. The notice places the project contact address in Kemen Port New Energy Industrial Park, Kengyuan, Lianjiang, Fujian.

Beijing Valve General Factory and Jinggong Valve Group rank second and third, quoting RMB 2.93 million and RMB 3.116 million respectively. All three list delivery within 30 days after contract signing, subject to the project team’s schedule. The public notice does not provide a valve quantity, size or material schedule.

The provisional-result period runs from November 3 to November 5. Written objections may be submitted during that period, with procurement suspended pending the purchaser’s reply. The notice therefore establishes evaluation rankings and provisional selection; it does not establish a signed supply contract or completed delivery.

02
EDITORIAL INTERPRETATION

Why it matters

Editorial analysis: This is a specific valve procurement milestone for an electrolyte installation. Package bids cannot be converted into unit valve prices without quantities and specifications.

Relevant toChemical valve suppliers, EPC buyers and battery-material equipment teams

03

What to watch next

Check the final award, contractual supply scope and delivery schedule following the objection period.

These are research prompts, not announced tenders or confirmed subsequent developments.

SOURCE & VERIFICATION

湖北联投咨询管理有限公司/湖北省招标投标协会

胜华连江20万吨锂电池电解液安装工程项目—阀门材料采购(第2次采购)预成交结果公示

This is an independently written summary and analysis, not an official translation. Project plans and status may change.