PipeChina reports 1.2 bcm/day peak capability; Hulin–Changchun awaits commissioning
The winter update separates operating upgrades from projects still preparing for commissioning and details storage and compressor maintenance.

The story explained
PipeChina’s 16 November update puts national-network peak delivery capability at 1.2 billion cubic metres per day, 30 million above the comparable period. This measures peak capability rather than actual daily throughput.
Three priority projects, including the Quzhou compressor-station upgrade, entered service before winter. Joint operation of sections of the third and second West–East pipelines added 20 million cubic metres per day of trunkline capacity. Hulin–Changchun has completed construction but remains in commissioning preparation; its stated annual capacity after commissioning is 10 billion cubic metres.
The Wen23, Jintan and Liuzhuang storage sites completed injection, with combined maximum withdrawal capability of 65 million cubic metres per day. LNG terminal inventories exceeded 1.05 billion cubic metres of gas. More than 400 compressor units underwent pre-winter checks, alongside maintenance and emergency preparations. The update does not disclose new valve-purchase contracts.
Why it matters
Editorial assessment: Commissioning handovers and peak operations put attention on compression, metering, storage and interlocks; capacity figures are not equipment orders.
Relevant toProject owners, EPCs, valve, pump and process-control professionals
What to watch next
Watch for Hulin–Changchun commissioning and storage-withdrawal or maintenance updates.
These are research prompts, not announced tenders or confirmed subsequent developments.
国家管网集团 / PipeChina
国家管网集团全面打响保供攻坚战
This is an independently written summary and analysis, not an official translation. Project plans and status may change.