ChemicalsProject watch

Catch-up: Sedin awards steam-trap, sampling and pressure-relief packages

Curated by valve.market · China
Persistent browser storage is unavailable.
IN BRIEF

Four notices dated 14 November are grouped in one update; the original steam-trap tender identifies Lutianhua's 100,000-tonne-per-year fine-chemicals project.

Added: 2026.11.16Source language: Chinese
Pressure-gauge and valve illustration; not the Lutianhua site or awarded equipment.
Pressure-gauge and valve illustration; not the Lutianhua site or awarded equipment. Image: Pierre Goiffon / Unsplash
OrganizationsSedin Engineering / Sichuan Lutianhua Oleochemical
Location / scopeSichuan
Announced stageAward notices
01

The story explained

Four Sedin Engineering notices dated 14 November identify successful suppliers for steam traps, a sampling system, pressure-relief manholes and rupture discs. This is a catch-up update. References are E134.C00.P02.56-019, -020, -021 and -022, respectively; the related E134-series results are grouped as one procurement development.

Gansu Hongfeng Machinery won the steam-trap package and Jiangsu Tianyu Petrochemical Metallurgical Equipment the sampling system. Shanghai Kaifan Petrochemical Equipment won the pressure-relief manholes and Shenyang Xinguang Aerospace Safety Systems the rupture discs. Each is an award following open negotiations, rather than a candidate ranking.

Matching the complete steam-trap procurement reference to the original 15 October tender identifies the EPC contract for Sichuan Lutianhua Oleochemical’s 100,000-tonne-per-year green fine-chemicals project. The other three results use the same E134.C00 series but do not repeat installation locations or plant units. Sedin’s Taiyuan office address is not treated as the project site.

The award notices disclose no quantities, pressure or temperature ratings, relief settings, sampling media or contract values. They also provide no delivery or operating-acceptance records. Suppliers have been selected, while equipment configurations and site acceptance remain to be established from subsequent documentation.

Related official notices: Sampling-system award; Pressure-relief-manhole award; Rupture-disc award; Original steam-trap tender identifying the project

02
EDITORIAL INTERPRETATION

Why it matters

Editorial assessment: The packages concern condensate drainage, sampling and overpressure protection. Supplier selection does not replace duty or safety-setting review.

Relevant toProject owners, EPC contractors and valve, pump and process-control specialists

03

What to watch next

Follow technical specifications, supply lists, plant-unit allocation and delivery and acceptance milestones.

These are research prompts, not announced tenders or confirmed subsequent developments.

SOURCE & VERIFICATION

赛鼎工程/中国化学电子招标投标交易平台

赛鼎公司-疏水阀成交公告

This is an independently written summary and analysis, not an official translation. Project plans and status may change.