Shendong tenders irrigation-pipeline relocation including six gate valves
Shendong's October 23 tender seeks relocation of existing irrigation pipelines across the planned site of the Ordos coal-liquefaction upgrading demonstration project.

The story explained
Shendong’s October 23 tender seeks relocation of existing irrigation pipelines across the planned site of the Ordos coal-liquefaction upgrading demonstration project.
Reference CEZB260608955 covers works south of the coal-to-liquids plant in Ulan Mulun. Scope includes 2,057m of relocated and new DN700 pipe, 2,057m each of new DN400 and DN300 pipe, and 150m of DN500 precast concrete casing.
The scope also lists six steel gate valves and six washout tees. The planned 350-calendar-day programme runs December 1, 2026 to November 16, 2027, subject to the purchaser’s actual start authorisation.
Documents close at 16:00 October 29; bids and opening are at 09:00 November 13, Beijing time. The single package excludes consortia and requires qualifying municipal-construction credentials and completed pipeline references. No valve supplier is separately appointed.
Why it matters
Some valve quantities are explicit, but they form part of a construction package rather than a separate valve award.
Relevant toValve, pump, actuator, process-control and engineering procurement professionals
What to watch next
Watch the construction award, detailed material requirements and actual start date.
These are research prompts, not announced tenders or confirmed subsequent developments.
国能e招
神东煤炭补连塔煤矿生态灌溉管道煤制油段改移工程公开招标项目招标公告
This is an independently written summary and analysis, not an official translation. Project plans and status may change.