Snøhvit Future estimate rises to NOK 26.5 billion; timetable unchanged
Equinor’s 7 October update retains 2029 compression and 2030 electrification targets. The figure is a project estimate, not an equipment quotation.

The story explained
Equinor now estimates Snøhvit Future at NOK 26.5 billion in 2026 money. This is a project budget; comparisons between estimate versions require consistent price bases.
The company cites the complexity of working within an operating LNG facility, alongside operational, weather and cable-tunnel rock challenges. This is an execution update, rather than a new capacity award.
Onshore compression remains planned for 2029 and electrification for 2030. Compression supports plateau production as reservoir pressure falls; electrification aims to reduce plant emissions. Both dates remain targets.
Why it matters
Editorial analysis: outage windows, isolation arrangements and interfaces between existing and new systems merit scrutiny. A rise in total project cost cannot be translated proportionally into additional valve purchasing.
Relevant toLNG modifications, EPC, flow-control and project-cost teams
What to watch next
Track budget versions, construction and outage arrangements, formal package changes and actual service-entry dates.
These are research prompts, not announced tenders or confirmed subsequent developments.