thyssenkrupp opens Duisburg hydrogen tender for deliveries from 2031
The first tranche targets 20,000–40,000 metric tons per year, subject to bids and commercial terms.

The story explained
thyssenkrupp Steel announced a new hydrogen supply tender for its Duisburg direct-reduction plant on November 23. The first tranche is expected to cover 20,000–40,000 metric tons annually from 2031. Final awarded volume will depend on bids and commercial terms. Suppliers may register until December 17, before the bidding phase begins.
The plant will initially use natural gas during ramp-up. Hydrogen is intended to replace part of that gas from 2031, with full hydrogen operation planned later. The announcement therefore describes a procurement process and phased fuel transition, rather than an operating all-hydrogen facility or a completed supply contract.
Design capacity is 2.5 million metric tons of direct-reduced iron annually. Two downstream smelters have combined capacity of 2.3 million metric tons of hot metal per year. The configuration is intended to integrate with existing steelmaking and downstream processes; those figures represent design capacity, not current output.
Why it matters
Editorial assessment: phased fuel changes make supply interfaces, metering and isolation-control compatibility relevant. No valve or actuator supplier is confirmed.
Relevant toValve, pump, actuator, process-control and engineering procurement professionals
What to watch next
Follow registration closure, awarded volumes, commercial conditions and the 2031 supply timetable.
These are research prompts, not announced tenders or confirmed subsequent developments.