FERC schedules environmental review for Tres Palacios Smith cavern expansion
A November 24 Federal Register notice schedules the EA for February 26, 2027; the expansion remains proposed.

The story explained
The November 24 Federal Register published FERC’s environmental-review schedule for the Tres Palacios Smith Cavern Expansion, docket CP26-556-000. The notice is dated November 18. An environmental assessment is planned for February 26, 2027, with May 27 identified for other applicable federal authorization decisions. This is a review timetable, not construction approval.
The Texas proposal would convert three brine caverns into storage with 24.8 Bcf of working gas and 8.93 Bcf of base gas, totaling 33.73 Bcf. The application was filed July 22; the newly reported milestone is the review schedule.
Proposed works include a 5.4-mile, 36-inch pipeline loop and three 1.7-mile, 16-inch laterals. El Campo would receive four 5,500 hp reciprocating compressors; existing facilities would gain three more, six cooling bays and a dehydration system. Three metering/regulation stations would be modified. These are proposed facilities, not awarded equipment contracts.
Why it matters
Editorial assessment: Compression, dehydration and metering create relevant engineering scope; approvals and procurement milestones determine actual opportunities.
Relevant toValve, pump, actuator, process-control and engineering procurement professionals
What to watch next
Watch the EA and schedule changes; May 27 is not a guaranteed approval or construction date.
These are research prompts, not announced tenders or confirmed subsequent developments.
FERC / U.S. Government Publishing Office
Tres Palacios Gas Storage LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Tres Palacios Smith Cavern Expansion Project