Dagang replacement project completes Unit 6 boiler acid cleaning
China Energy Engineering reports a boiler-cleaning milestone for Unit 6 at the two-unit, 1,320 MW Dagang replacement project.

The story explained
China Energy Engineering said on 21 November that boiler acid cleaning for Unit 6 at the Dagang replacement project was completed on 17 November. Anhui No. 2 Power Construction undertook the work. The announcement identifies a commissioning step, without reporting grid connection or commercial operation.
The Tianjin Binhai project comprises two 660 MW ultra-supercritical coal-fired units. Its associated environmental systems cover dust removal, desulfurization, denitrification and treatment of desulfurization wastewater.
The company projects annual generation of 5.94 billion kWh after completion, serving the Beijing–Tianjin–Tangshan load centre and supplying heat to Binhai. This is a prospective operating figure, not electricity already generated at the cleaning milestone.
Why it matters
The milestone shifts attention to subsequent steam-water commissioning and auxiliary-system interfaces; it does not establish a new valve order.
Relevant toValve, pump and process-control manufacturers; project engineers and procurement teams
What to watch next
Track subsequent commissioning, grid-connection and heat-supply milestones and documented equipment acceptance.
These are research prompts, not announced tenders or confirmed subsequent developments.