The November 4 works tender covers aerogel insulation and removable modules for existing equipment, rather than wholesale valve replacement.

Added: 2026.11.05Source language: Chinese
Industrial equipment and piping illustration; not the Shanghaimiao retrofit site.
Industrial equipment and piping illustration; not the Shanghaimiao retrofit site. Image: Dave Meckler / Unsplash
OrganizationsCHN Energy Inner Mongolia Shanghaimiao Power Generation
Location / scopeShanghaimiao, Ordos, Inner Mongolia
Announced stageWorks tender
01

The story explained

CHN Energy’s Shanghaimiao power company issued works tender CEZB260109341 on November 4, 2026 for boiler-pipe, valve and equipment safety protection. The scope serves four existing 1,000 MW units operated by two companies at Shanghaimiao in Ordos, Inner Mongolia.

Work includes measuring, fabricating and installing coupling guards, electrical and instrumentation protection covers, and repairs to damaged or overheating pipe insulation and steam/water valve casings. High-temperature pipe insulation on the turbine hall’s 17-metre level will be removed, with waste disposal, and replaced by aerogel insulation and outer cladding.

Selected pipe and valve insulation that requires repeated removal for maintenance will be converted to reusable, formed-metal removable modules. The stated objective is easier dismantling and shorter maintenance work. This is a protection and insulation package, not confirmation of new generating capacity or replacement of the valves themselves.

Completion is required within one year after contract signing, subject to the owner’s work windows. Documents close November 9 at 11:00 and bids November 24 at 11:00, Beijing time. Applicants need the specified insulation-contractor qualification, safety permit and relevant power-plant guarding references; joint bids are excluded.

02
EDITORIAL INTERPRETATION

Why it matters

Editorial analysis: The opportunity concerns thermal protection and maintainability around existing valves and piping, with a stronger link to insulation modules and site services than new valve supply.

Relevant toValve, pump and process-control suppliers; EPC and plant operations teams

03

What to watch next

Check survey quantities, removable-module acceptance criteria, outage access and the final works award.

These are research prompts, not announced tenders or confirmed subsequent developments.

SOURCE & VERIFICATION

国能e招

国电电力上海庙能源及上海庙发电公司锅炉管道、阀门、设备安全防护设施完善工程公开招标项目招标公告

This is an independently written summary and analysis, not an official translation. Project plans and status may change.